Data in euro
Updated on 28/02/2025

Cohesion programmes

Which Programmes have more implemented projects?

Source Programme Value
Fondo Aree Sottoutilizzate 2000-2006 PSC REGIONE BASILICATA 849,354
Data in euro
Updated on 28/02/2025

Cohesion programmes

Which Programmes have more implemented projects?

Source Programme Value
Fondo Aree Sottoutilizzate 2000-2006 PSC REGIONE BASILICATA 849,354
Data in euro
Updated on 28/02/2025

Cohesion programmes

Which Programmes have more implemented projects?

Source Programme Value
Fondo Aree Sottoutilizzate 2000-2006 PSC REGIONE BASILICATA 834,878
Data in euro
Updated on 28/02/2025

Cohesion programmes

Which Programmes have more implemented projects?

Source Programme Value
Fondo Aree Sottoutilizzate 2000-2006 PSC REGIONE BASILICATA 834,878
Data in number of projects
Updated on 28/02/2025

Cohesion programmes

Which Programmes have more implemented projects?

Source Programme Value
Fondo Aree Sottoutilizzate 2000-2006 PSC REGIONE BASILICATA 1

Implementing bodies with most funding

ACQUEDOTTO LUCANO S.p.A. € 849,354

Developments in total commitments and payments

What has been allocated and paid over the years?

Year Commitments Payments
2007 849354.21 34285.41
2008 849354.21 70818.21
2009 849354.21 518641.58
2010 849354.21 634616.29
2011 849354.21 789492.07
2012 849354.21 819878.05
2013 849354.21 819878.05
2014 849354.21 834878.05

Projects with most funding

RIFACIMENTO E ADEGUAMENTO RETE IDRICA, FOGNARIA E DEPURATORE € 849,354

Projects completed most recently

04/08/2011
RIFACIMENTO E ADEGUAMENTO RETE IDRICA, FOGNARIA E DEPURATORE

Funding per capita

Comune di Gorgoglione € 985

The entirety of project funding is associated with the municipality, even when a project is located in multiple municipalities. Population numbers are as at 31/12/2022 (source: ISTAT).