CUP: E82F23000260001
di MESSA IN SICUREZZA DI VIA TERAMO VIA SICILIA E VIA G. PASCOLI MEDIANTE SISTEMAZIONE,RIPRISTINI DEL SOTTOFONDO ED ASFALTATURA
SUMMARY OF THE PROJECT
di MESSA IN SICUREZZA DI VIA TERAMO VIA SICILIA E VIA G. PASCOLI MEDIANTE SISTEMAZIONE,RIPRISTINI DEL SOTTOFONDO ED ASFALTATURA
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 30,556.62
of which cohesion funds
€ 30,556.62
Given name | Amount |
---|---|
Development and Cohesion Fund | 30556.62 |
- Economies:
- € 751.38
Payments monitored
€ 29,027.46
of which cohesion funds
€ 29,027.46
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 29027.46 | 29027.46 | 94 |
State of progress
Open
Expected start: 10/07/2023
Effective start: 10/07/2023
Expected end: 02/08/2023
Effective end: 02/08/2023
Entities
- Planning body
- COMUNE DI MOSCUFO
- Beneficiary
- COMUNE DI MOSCUFO
- Executor
- COMUNE DI MOSCUFO
Programming area
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 30,556.62
- Payments on cohesion funds
- € 29,027.46
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali