CUP: C97H17001280002
SUB-INTERVENTO 3 AREA VESTINA ZONA 3 SS PP NN 5-6-13-14-20-21-23-28-29-30
SUMMARY OF THE PROJECT
SUB-INTERVENTO 3 AREA VESTINA ZONA 3 SS PP NN 5-6-13-14-20-21-23-28-29-30
Implementation indicator
Progetti per la fruizione integrata e la promozione
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 1,628,526.05
of which cohesion funds
€ 1,628,526.05
Given name | Amount |
---|---|
Development and Cohesion Fund | 1628526.05 |
- Economies:
- € 536,473.95
Payments monitored
€ 1,567,070.33
of which cohesion funds
€ 1,567,070.33
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 384947.95 | 384947.95 | 23 |
2020 | 932820.55 | 1317768.50 | 80 |
2021 | 149206.00 | 1466974.50 | 90 |
2022 | 75593.33 | 1542567.83 | 94 |
2023 | 24502.50 | 1567070.33 | 96 |
State of progress
Completed
Expected start: 01/08/2018
Effective start: 04/11/2019
Expected end: 15/07/2022
Effective end: 14/05/2021
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI PESCARA
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI PESCARA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto Stradale