CUP: F23G15000390002
DIAGNOSI ENERGETICHE PER VERIFICARE IL CONSUMO DI ENERGIA DEGLI IMPIANTI INSTALLATI
SUMMARY OF THE PROJECT
REALIZZAZIONE DIAGNOSI ENERGETICHE SU EDIFICI PUBBLICI DESTINATI AD USO PUBBLICO DI PROPRIETÃ DEL COMUNE DI FERENTILLO
Download project
Funding monitored
€ 4,499.99
of which cohesion funds
€ 4,094.25
Given name | Amount |
---|---|
European Union | 2047.13 |
Revolving Fund | 1432.99 |
Region | 614.13 |
Another public source | 405.74 |
Payments monitored
€ 4,499.99
of which cohesion funds
€ 4,094.25
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 4499.99 | 4499.99 | 100 |
State of progress
Completed
Expected start: 14/10/2015
Effective start: 14/10/2015
Expected end: 29/02/2016
Effective end: 31/12/2016
Entities
- Planning body
- REGIONE UMBRIA
- Beneficiary
- COMUNE DI FERENTILLO
- Executor
- ING. BEATRICE MARCONI
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF UMBRIA
- Axis
- ENERGIA SOSTENIBILE
- Specific objective