CUP: F61E17000180002
Ampliamento rete fognaria acque nere
SUMMARY OF THE PROJECT
Ampliamento rete fognaria acque nere
Implementation indicator
Popolazione addizionale servita dall'approvvigionamento idrico potenziato
- Target
- 1,000 num
- Achieved
- 1,000 num
Download project
Funding monitored
€ 508,263.75
of which cohesion funds
€ 438,263.75
Given name | Amount |
---|---|
Development and Cohesion Fund | 438263.75 |
Another public source | 70000.00 |
Payments monitored
€ 288,285.57
of which cohesion funds
€ 288,285.57
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 288285.57 | 288285.57 | 56 |
State of progress
Open
Expected start: 03/10/2019
Effective start: 03/10/2019
Expected end: 25/01/2022
Effective end: 25/01/2022
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- COMUNE DI ALTAVILLA IRPINA
- Executor
-
ING. ANGELO DI GENNARO
CONSORZIO STABILE MEDIL S.C.A.R.L
Programming area
- Programme
- PSC CAMPANIA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 438,263.75
- Payments on cohesion funds
- € 288,285.57
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche