CUP: H98B23000020009
LAVORI DI MANUTENZIONE STRAORDINARIA E SEZIONAMENTO DELLA RETE IDRICA COMUNALE
SUMMARY OF THE PROJECT
LAVORI DI MANUTENZIONE STRAORDINARIA E SEZIONAMENTO DELLA RETE IDRICA COMUNALE
Implementation indicator
Popolazione addizionale servita dall'approvvigionamento idrico potenziato
- Target
- 9,600 num
- Achieved
- 9,600 num
Funding monitored
€ 179,044.21
of which cohesion funds
€ 179,044.21
Given name | Amount |
---|---|
European Union | 134283.16 |
Revolving Fund | 31332.74 |
Region | 13428.31 |
- Economies:
- € 955.79
Payments monitored
€ 174,076.26
of which cohesion funds
€ 174,076.26
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 174076.26 | 174076.26 | 97 |
State of progress
Completed
Expected start: 01/10/2023
Effective start: 23/10/2023
Expected end: 30/11/2023
Effective end: 11/12/2023
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- COMUNE DI CESA
- Executor
-
ROCCO GAETANO
EDILMONTE DI MONTELLA MASSIMO
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF CAMPANIA
- Axis
- TUTELA E VALORIZZAZIONE DEL PATRIMONIO AMBIENTALE E CULTURAL
- Specific objective
- MIGLIORAMENTO DEL SERVIZIO IDRICO INTEGRATO PER USI CIVILI E RIDUZIONE DELLE PERDITE DI RETE DI ACQUEDOTTO