CUP: D78C20000250002
Miglioramento viabilità e sicurezza stradale - Comune di Nola
SUMMARY OF THE PROJECT
Miglioramento viabilità e sicurezza stradale - Comune di Nola
Implementation indicator
Lunghezza totale delle strade di nuova costruzione
- Target
- 1 km
- Achieved
- 0 km
Download project
Funding monitored
€ 1,645,237.07
of which cohesion funds
€ 1,645,237.07
Given name | Amount |
---|---|
Development and Cohesion Fund | 1645237.07 |
- Economies:
- € 147.51
Payments monitored
€ 1,288,356.68
of which cohesion funds
€ 1,288,356.68
78%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 780975.19 | 780975.19 | 47 |
2024 | 507381.49 | 1288356.68 | 78 |
State of progress
Open
Expected start: 30/11/2023
Effective start: 30/11/2023
Expected end: 30/09/2025
Effective end: not available
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- COMUNE DI NOLA
- Executor
-
GLOROA SRL
COMUNE DI NOLA
Programming area
- Programme
- FSC ANTICIPAZIONI CAMPANIA 2021-2027
- 2021-2027 National Development and Cohesion Fund
- 2021-2027 National Development and Cohesion Fund
- Cohesion funds
- € 1,645,237.07
- Payments on cohesion funds
- € 1,288,356.68
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana
Other projects in territory
Same theme
Avviso 3/2016 CAM_35 | € 1,897,320 |
'Rete Territoriale Solidale' - N23 Nola | € 1,057,549 |
Sostegno alla gestione per strutture/servizi a titolarità pubblica dell'Ambito N23 del Comune di Nola | € 652,434 |
assistenza domiciliare sociale N23 | € 641,747 |
nidi d'infanzia N23 | € 640,286 |