CUP: F36G22000470006
DGR 335 DEL 28/06/2022. PIANO TRIENNALE DI MANUTENZIONE STRADE - FASE 1 - SERVIZI DI MANUTENZIONE DELLA RETE STRADALE DELLA PROVINCIA DI AVELLINO
SUMMARY OF THE PROJECT
DGR 335 DEL 28/06/2022. PIANO TRIENNALE DI MANUTENZIONE STRADE - FASE 1 - SERVIZI DI MANUTENZIONE DELLA RETE STRADALE DELLA PROVINCIA DI AVELLINO
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 598.56 km
- Achieved
- 0 km
Funding monitored
€ 11,761,745.13
of which cohesion funds
€ 11,761,745.13
Given name | Amount |
---|---|
Revolving Fund | 11761745.13 |
Payments monitored
€ 8,265,229.14
of which cohesion funds
€ 8,265,229.14
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 6978021.32 | 6978021.32 | 59 |
2024 | 1287207.82 | 8265229.14 | 70 |
State of progress
Open
Expected start: 18/11/2022
Effective start: not available
Expected end: 19/05/2024
Effective end: not available
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE AVELLINO
- Executor
- ANC COSTRUZIONI
Programming area
- 2014-2020 Cohesion Action Plan
- 2014-2020 Cohesion Action Plan
- Programme
- POC CAMPANIA
- CAP area axis
- Trasporti e mobilità
- CAP action line
- Efficientamento ed integrazione della viabilità, anche promuovendo la mobilità e miglioramento della sicurezza stradale