ADEGUAMENTO IMPIANTO DI PUBBLICA ILLUMINAZIONE PER IL CONTENIMENTO DELL'INQUINAMENTO LUMINOSO E RISPARMIO ENERGETICO IN CONFORMITA' AL PIC -SAN GIORGIO DEL SANNIO -
SUMMARY OF THE PROJECT
ADEGUAMENTO IMPIANTO DI PUBBLICA ILLUMINAZIONE PER IL CONTENIMENTO DELL'INQUINAMENTO LUMINOSO E RISPARMIO ENERGETICO IN CONFORMITA' AL PIC -SAN GIORGIO DEL SANNIO -
Implementation indicator
Punti illuminanti/luce
- Target
- 1,230 num
- Achieved
- 1,230 num
Download project
Funding monitored
€ 2,428,684.93
of which cohesion funds
€ 2,428,684.93
Given name | Amount |
---|---|
European Union | 1821513.70 |
Revolving Fund | 425019.87 |
Region | 182151.36 |
- Economies:
- € 182,024.87
Payments monitored
€ 2,428,684.93
of which cohesion funds
€ 2,428,684.93
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 2428684.93 | 2428684.93 | 100 |
State of progress
Completed
Expected start: 01/05/2023
Effective start: 20/09/2023
Expected end: 31/10/2023
Effective end: 12/12/2023
Entities
Programming area
- Programme
- ROP ERDF CAMPANIA
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 2,428,684.93
- Payments on cohesion funds
- € 2,428,684.93
- Axis
- ENERGIA SOSTENIBILE
- Specific objective
- RIDUZIONE DEI CONSUMI ENERGETICI NEGLI EDIFICI E NELLE STRUTTURE PUBBLICHE O AD USO PUBBLICO RESIDENZIALI E NON RESIDENZIALI E INTEGRAZIONE DI FONTI RINNOVABILI