CUP: F27F13000040006
CMSM-PO-5A REVAMPING N.7 ELETTROTRENI DELLA SERIE T 21 LOTTO 5A
SUMMARY OF THE PROJECT
REVAMPING DI 7 ELETTROTRENI
Implementation indicator
Lunghezza totale delle linee tranviarie e metropolitane nuove o migliorate
- Target
- 1 km
- Achieved
- 0 km
Funding monitored
€ 11,302,429.75
of which cohesion funds
€ 11,302,429.75
Given name | Amount |
---|---|
Development and Cohesion Fund | 11302429.75 |
- Economies:
- € 157,500.00
Payments monitored
€ 9,285,691.53
of which cohesion funds
€ 9,285,691.53
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 9285691.53 | 9285691.53 | 82 |
State of progress
Open
Expected start: 10/06/2015
Effective start: 10/06/2015
Expected end: 31/12/2024
Effective end: not available
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- ENTE AUTONOMO VOLTURNO SRL
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CAMPANIA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario