CUP: G11E17000180001
AMPLIAMENTO, RISTRUTTURAZIONE E POTENZIAMENTO DELLA RETE IDRICA COMUNALE - SOSTITUZIONE DEL TRATTO DI RETE IDRICA CONSORTILE DI ADDUZIONE ALLA RETE IDRICA URBANA
SUMMARY OF THE PROJECT
AMPLIAMENTO, RISTRUTTURAZIONE E POTENZIAMENTO DELLA RETE IDRICA COMUNALE - SOSTITUZIONE DEL TRATTO DI RETE IDRICA CONSORTILE DI ADDUZIONE ALLA RETE IDRICA URBANA
Implementation indicator
Superficie oggetto di intervento
- Target
- 1 mq
- Achieved
- 0 mq
Funding monitored
€ 3,300,000.00
of which cohesion funds
€ 3,300,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3300000.00 |
Payments monitored
€ 2,081,271.22
of which cohesion funds
€ 2,081,271.22
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 2081271.22 | 2081271.22 | 63 |
State of progress
Open
Expected start: 03/02/2021
Effective start: 03/02/2021
Expected end: 04/08/2025
Effective end: not available
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- COMUNE DI SANTA MARIA LA FOSSA
- Executor
- REGIONE CAMPANIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CAMPANIA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche