CUP: D12I17000280002
REALIZZAZIONE IMPIANTO DI TRATTAMENTO DEL PERCOLATO PRESSO LA DISCARICA PARCO SAURINO I, II PIU' AMPLIAMENTO
SUMMARY OF THE PROJECT
REALIZZAZIONE IMPIANTO DI TRATTAMENTO DEL PERCOLATO PRESSO LA DISCARICA PARCO SAURINO I, II PIU' AMPLIAMENTO
Implementation indicator
Capacita' smaltimento rifiuti oggetto di intervento
- Target
- 72,000 ton/a
- Achieved
- 0 ton/a
Download project
Funding monitored
€ 3,756,616.20
of which cohesion funds
€ 3,756,616.20
Given name | Amount |
---|---|
Development and Cohesion Fund | 3756616.20 |
- Economies:
- € 1,243,383.80
Payments monitored
€ 3,536,458.64
of which cohesion funds
€ 3,536,458.64
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 3536458.64 | 3536458.64 | 94 |
State of progress
Open
Expected start: 14/12/2019
Effective start: 14/12/2019
Expected end: 30/11/2025
Effective end: not available
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI CASERTA
- Executor
- REGIONE CAMPANIA
Programming area
- Programme
- PSC CAMPANIA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 3,756,616.20
- Payments on cohesion funds
- € 3,536,458.64
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rifiuti