Updated on 30/04/2025
Funding monitored € 13,000,000.00 of which cohesion funds € 13,000,000.00
Given name Amount
Development and Cohesion Fund13000000.00
Payments monitored € 10,808,942.41 of which cohesion funds € 10,808,942.41
Year Amount Cumulative amount Percentage on public financing
202210748987.2610748987.2682
2023010748987.2682
202459955.1510808942.4183

State of progress

Open
Expected start: 25/05/2009
Effective start: 25/05/2009
Expected end: 15/09/2021
Effective end: 15/09/2021

Type

Theme

Territory

Entities

Planning body
REGIONE CAMPANIA
Beneficiary
REGIONE CAMPANIA
Executor
GIOVANNI MALINCONICO S.P.A.

Programming area

Programme
PSC CAMPANIA
Fondo Aree Sottoutilizzate 2000-2006
2000-2006 Underutilized Areas Fund
Cohesion funds
€ 13,000,000.00
Payments on cohesion funds
€ 10,808,942.41
Policy Area
Ambiente e risorse naturali
Sector of intervention
Rischi e adattamento climatico