CUP: I85H16000020001
LAVORI DI RIFACIMENTO STRAORDINARIO DELLA RETE IDRICA COMUNALE E CAPTAZIONE IDRICA. COMUNE DI RUVIANO
SUMMARY OF THE PROJECT
IL PRESENTE PROGETTO HA COME OBIETTIVO L'APPROVVIGIONAMENTO DI ACQUA DA DESTINARE AL CONSUMO UMANO DA ALTRE FONTI DISPONIBILI NELL'AMBITO DEL TERRITORIO COMUNALE DI RUVIANO CON RIFACIMENTO STRAORDINARIO DELLE RETE IDRICA COMUNALE.
Download project
Funding monitored
€ 145,634.17
of which cohesion funds
€ 145,634.17
Given name | Amount |
---|---|
Revolving Fund | 145634.17 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 01/01/2024
Effective start: not available
Expected end: 29/07/2024
Effective end: not available
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- COMUNE DI RUVIANO
Programming area
- 2014-2020 Cohesion Action Plan
- 2014-2020 Cohesion Action Plan
- Programme
- POC CAMPANIA
- CAP area axis
- Ambiente e territorio
- CAP action line
- Interventi mirati ad accrescere la capacità di offerta, la qualità  e l'efficenza del servizio idrico integrato, per la riduzione degli sprechi e l'innalzamento del livello di qualità dei corpi id