CUP: G77H18001140002
LAVORI DI MESSA IN SICUREZZA DI VIABILITA' COMUNALE - VIA FIUME CALORE, VIA TORRE DEI ROCCI, VIA ACQUOLEILA, VIA CAMPORA, VIA PIESCO
SUMMARY OF THE PROJECT
LAVORI DI MESSA IN SICUREZZA DI VIABILITA' COMUNALE - VIA FIUME CALORE, VIA TORRE DEI ROCCI, VIA ACQUOLEILA, VIA CAMPORA, VIA PIESCO
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Funding monitored
€ 986,568.12
of which cohesion funds
€ 986,568.12
Given name | Amount |
---|---|
Development and Cohesion Fund | 986568.12 |
- Economies:
- € 13,118.88
Payments monitored
€ 899,718.23
of which cohesion funds
€ 899,718.23
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 4692.33 | 4692.33 | 0 |
2021 | 495151.13 | 499843.46 | 50 |
2022 | 399874.77 | 899718.23 | 91 |
State of progress
Open
Expected start: 03/09/2020
Effective start: 15/06/2020
Expected end: 30/06/2022
Effective end: 29/12/2021
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- COMUNE DI CASSANO IRPINO
- Executor
-
THEMA ENERGIA SRL
RISOLI SALVATORE
PERSICO PASQUALE
PALMIERI SALVATORE
LANZILLO CIRIACO
GUARINO NICOLA
GALLUCCIO MAURO ELIO
BONETTI GIOVANNI
BOCCHINO SOCCORSO
BOCCHINO MUAURIZIO
Visualizzati i primi 10 soggetti di 11
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CAMPANIA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale