CUP: J51B15000530004
LAVORI DI COSTRUZIONE DELL'ASSE VIARIO DI COLLEGAMENTO TRA IL NUOVO CASELLO AUTOSTRADALE DI VIA S. ELENA E LA VIA NAZIONALE (SS18)-STRALCIO ASSE VIARIO DI COLLEGAMENTO TRA IL NUOVO SVINCOLO DI TORRE DEL GRECO E LA ROTONDA SU VIA LAMARIA - I LOTTO
SUMMARY OF THE PROJECT
IL PROGETTO PREVEDE LA COSTRUZIONE DI UN PERCORSO DI ACCESSO E FRUIZIONE DEL CENTRO CITTADINO CON LE MAGGIORI DIRETTRICI DI TRAFFICO VELOCE DEL TERRITORI, ATTRAVERSO LA PREVISIONE DI UN PERCORSO IN GRADO DI FAVORIRE L'ALLEGGERIMENTO DEI FLUSSI IN ENTRATA E IN USCITA DEL TRAFFICO VEICOLARE LEGGERO E DEGLI ACCESSI PEDONALI AI MAGGIORI SITI DI INTERESSE TURISTICO, CULTURALE E AI CENTRI PIù SIGNIFICATIVI PER LE POPOLAZIONI RESIDENTI, DEL COMPRENSORIO E DEI VISITATORI CHE ACCEDONO A TORRE DEL GRECO.
Funding monitored
€ 12,303,382.20
of which cohesion funds
€ 3,173,548.39
Given name | Amount |
---|---|
European Union | 2380161.29 |
Revolving Fund | 555370.97 |
Status: other measures | 905183.88 |
Region | 238016.13 |
Municipality | 8224649.93 |
Payments monitored
€ 3,173,548.39
of which cohesion funds
€ 3,173,548.39
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 1529974.50 | 1529974.50 | 12 |
2019 | 1643573.89 | 3173548.39 | 25 |
State of progress
Open
Expected start: 17/10/2018
Effective start: not available
Expected end: 31/12/2023
Effective end: not available
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- COMUNE DI TORRE DEL GRECO
- Executor
- ROAD HOUSE S.R.L.
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF CAMPANIA
- Axis
- SVILUPPO URBANO SOSTENIBILE
- Specific objective
- RIPOSIZIONAMENTO COMPETITIVO DELLE DESTINAZIONI TURISTICHE