CUP: F24D18000080002
COMUNE DI REINO_LAVORI DI COMPLETAMENTO INFRASTRUTTURE A RETE AREE PIP - FOGNATURE
SUMMARY OF THE PROJECT
LAVORI DI COMPLETAMENTO INFRASTRUTTURE A RETE AREE PIP - FOGNATURE
Implementation indicator
Popolazione addizionale beneficiaria del trattamento delle acque reflue potenziato
- Target
- 2 num
- Achieved
- 1 num
Funding monitored
€ 1,400,758.63
of which cohesion funds
€ 1,400,758.63
Given name | Amount |
---|---|
European Union | 1050568.97 |
Revolving Fund | 245132.76 |
Region | 105056.90 |
Payments monitored
€ 234,145.94
of which cohesion funds
€ 234,145.94
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 132501.95 | 132501.95 | 9 |
2021 | 0 | 132501.95 | 9 |
2022 | 101643.99 | 234145.94 | 16 |
State of progress
Open
Expected start: 19/05/2019
Effective start: 20/04/2020
Expected end: 14/01/2020
Effective end: not available
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- COMUNE DI REINO
- Executor
-
TOZZI S.R.L.
SOIL TEST SRL
PERIFANO LUIGI DIEGO
ING. AMEDEO DE MARCO - RTP DE MARCO CAPOGRUPPO
BOFFA PIETRO
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF CAMPANIA
- Axis
- TUTELA E VALORIZZAZIONE DEL PATRIMONIO AMBIENTALE E CULTURAL
- Specific objective
- MIGLIORAMENTO DEL SERVIZIO IDRICO INTEGRATO PER USI CIVILI E RIDUZIONE DELLE PERDITE DI RETE DI ACQUEDOTTO