CUP: B69J18002860002
LAVORI DI RIQUALIFICAZIONE DI VIALE AUGUSTO
SUMMARY OF THE PROJECT
LAVORI DI RIQUALIFICAZIONE DI VIALE AUGUSTO
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1.50 km
- Achieved
- 0 km
Download project
Funding monitored
€ 2,591,495.84
of which cohesion funds
€ 2,591,495.84
Given name | Amount |
---|---|
Revolving Fund | 2591495.84 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 08/07/2022
Effective start: not available
Expected end: 31/10/2023
Effective end: not available
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- COMUNE DI NAPOLI
- Executor
-
SOCIETA' DI INGEGNERIA V.E.G.A. S.R.L.
MOSTRAD SRL
Programming area
- 2014-2020 Cohesion Action Plan
- 2014-2020 Cohesion Action Plan
- Programme
- POC CAMPANIA
- CAP area axis
- Trasporti e mobilità
- CAP action line
- Efficientamento ed integrazione della viabilità, anche promuovendo la mobilità e miglioramento della sicurezza stradale