CUP: H57H15000880001
METANIZZAZIONE INFRASTRUTTURE - COMUNE DI AQUARA
SUMMARY OF THE PROJECT
INFRASTRUTTURE PER LA METANIZZAZIONE PER IL COMUNE DI AQUARA
Download project
Funding monitored
€ 1,552,500.00
of which cohesion funds
€ 1,552,500.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1552500.00 |
- Other resources - Private:
- € 1,322,500
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 01/01/2020
Effective start: 01/01/2020
Expected end: 31/01/2021
Effective end: 31/01/2021
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- COMUNE DI AQUARA
Programming area
- Programme
- PSC CAMPANIA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 172,500.00
- Payments on cohesion funds
- € 0.00
- Policy Area
- Energia
- Sector of intervention
- Reti e accumulo
- Programme
- METANIZZAZIONE MEZZOGIORNO
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 1,380,000.00
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture energetiche
Other projects in territory
Same theme
METANIZZAZIONE MISURATORI COMUNE DI AQUARA | € 141,426 |
Same type of investment
FONDOVALLE CALORE ¿ COMPLETAMENTO¿ : ¿ I LOTTO, II STRALCIO ¿ TRATTO A-B, SS166 PONTE CALORE - LOCALITà MAINARDO | € 41,953,835 |
COMPLETAMENTO STRUTTURA COMUNALE DA ADIBIRE A PUNTO SALUTE | € 18,744 |