CUP: E66J16000980002
SGTL3.1817L - 'LAVORI DI REALIZZAZIONE DI UN LABORATORIO ALTA TENSIONE (20.000V) PER PROVE DI CORTO CIRCUITO SU TRASFORMATORI E ADEGUAMENTO SPAZI PER ALLOCAZIONE ALTRI LABORATORI NEI MODULI 1 DEL COMPLESSO UNIVERSITARIO DI SAN GIOVANNI A TEDUCCIO'
SUMMARY OF THE PROJECT
REALIZZAZIONE DI UN LABORATORIO DI RICERCA E PROVE PER MACCHINE ED APPARECCHIATURE ELETTRICHE IN ALTA TENSIONE , FINO A 36KV
Implementation indicator
Superficie oggetto di intervento
- Target
- 340 mq
- Achieved
- 340 mq
Funding monitored
€ 2,311,454.89
of which cohesion funds
€ 2,311,454.89
Given name | Amount |
---|---|
Revolving Fund | 2311454.89 |
Payments monitored
€ 1,902,994.30
of which cohesion funds
€ 1,902,994.30
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 892816.64 | 892816.64 | 38 |
2018 | 196419.66 | 1089236.30 | 47 |
2019 | 340114.83 | 1429351.13 | 61 |
2020 | 473643.17 | 1902994.30 | 82 |
State of progress
Open
Expected start: 01/04/2019
Effective start: 19/07/2019
Expected end: 30/09/2019
Effective end: 02/03/2020
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- UNIVERSITA DEGLI STUDI DI NAPOLI FEDERICO II
- Executor
- ROMANO COSTRUZIONI & C. S.R.L.
Programming area
- 2014-2020 Cohesion Action Plan
- 2014-2020 Cohesion Action Plan
- Programme
- POC CAMPANIA
- CAP area axis
- Capitale umano e lavoro e politiche giovanili
- CAP action line
- Interventi infrastrutturali e immateriali mirati ad accrescere l'attrattività dell'offerta universitaria regionale (residenze universitarie, etc.)