CUP: E66B09000110002
MODULO A6-A7 - 'REALIZZAZIONE DEL LABORATORIO DEL NUOVO POLO MATERIALI DEL CNR'
SUMMARY OF THE PROJECT
RISTRUTTURAZIONE DEGLI EDIFICI ESISTENTI SU VIA SIGNORINI
Download project
Funding monitored
€ 14,688,545.11
of which cohesion funds
€ 14,688,545.11
Given name | Amount |
---|---|
European Union | 11016408.83 |
Revolving Fund | 2570495.39 |
Region | 1101640.89 |
Payments monitored
€ 10,948,489.71
of which cohesion funds
€ 10,948,489.71
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 1949177.83 | 1949177.83 | 13 |
2019 | 939523.29 | 2888701.12 | 19 |
2020 | 2765593.86 | 5654294.98 | 38 |
2021 | 1996665.99 | 7650960.97 | 52 |
2022 | 2746124.98 | 10397085.95 | 70 |
2023 | 551403.76 | 10948489.71 | 74 |
State of progress
Open
Expected start: 30/01/2018
Effective start: 30/01/2018
Expected end: 31/07/2023
Effective end: not available
Entities
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF CAMPANIA
- Axis
- INFRASTRUTTURE PER IL SISTEMA DI ISTRUZIONE REGIONALE
- Specific objective
- INNALZAMENTO DEI LIVELLI DI COMPETENZE, DI PARTECIPAZIONE E DI SUCCESSO FORMATIVO NELL'ISTRUZIONE UNIVERSITARIA E/O EQUIVALENTE