CUP: F46J16000540001
Riqualificazione energetica del Municipio
SUMMARY OF THE PROJECT
Riqualificazione energetica del Municipio: sistema composito di interventi che hanno come obiettivo l'efficientamento energetico del Municipio di Mel
Download project
Funding monitored
€ 104,937.51
of which cohesion funds
€ 83,050.43
Given name | Amount |
---|---|
European Union | 41525.22 |
Revolving Fund | 29067.65 |
Region | 12457.56 |
Municipality | 21887.08 |
Payments monitored
€ 104,937.51
of which cohesion funds
€ 83,050.43
100%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 45527.10 | 45527.10 | 43 |
2018 | 59410.41 | 104937.51 | 100 |
State of progress
Completed
Expected start: 11/07/2017
Effective start: 11/07/2017
Expected end: 03/09/2018
Effective end: 03/09/2018
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- COMUNE DI BORGO VALBELLUNA
- Beneficiary
- COMUNE DI BORGO VALBELLUNA
- Executor
-
UNIONE MONTANA FELTRINA
TERMOIDRAULICA DI MASCHERA GIORGIO
STUDIO DI INGEGNERIA EDI MENEGUZ E LUCA STEFANI
SCARTON LEILA
DIand DI DI DE PICCOLI S.and DE PICCOLI F.and C. SNC
COMUNE DI MEL
CASTELLANA RESTAURI SRL
AUTORITA PER LA VIGILANZA SUI CONTRATTI PUBBLICI DI LAVORI, SERVIZI E FORNITURE
Programming area
- Programme
- ROP ERDF VENETO
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 83,050.43
- Payments on cohesion funds
- € 83,050.43
- Axis
- SOSTENIBILITA' ENERGETICA E QUALITA' AMBIENTALE
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili (RA 4.1 AdP)
Other projects in territory
Same theme
Same type of investment
INTERVENTI DI RIQUALIFICAZIONE ENERGETICA CSA "ROSA ED ETTORE MIONE" DI LENTIAI VIA PIAVE 60 | € 196,303 |