CUP: B64H15003000006
ALBEROBELLO - RIQUALIFICAZIONE SCUOLA DELL'INFANZIA "G. NOTARNICOLA" E SCUOLA PRIMARIA "M. LA SORTE
SUMMARY OF THE PROJECT
ALBEROBELLO - RIQUALIFICAZIONE SCUOLA DELL'INFANZIA "G. NOTARNICOLA" E SCUOLA PRIMARIA "M. LA SORTE
Implementation indicator
Numero di allievi beneficiari (Istruzione)
- Target
- 265 num
- Achieved
- 270 num
Download project
Funding monitored
€ 922,741.61
of which cohesion funds
€ 922,741.61
Given name | Amount |
---|---|
Development and Cohesion Fund | 922741.61 |
Payments monitored
€ 185,304.03
of which cohesion funds
€ 185,304.03
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 185304.03 | 185304.03 | 20 |
State of progress
Open
Expected start: 01/08/2017
Effective start: not available
Expected end: 28/02/2018
Effective end: not available
Entities
- Planning body
- REGIONE PUGLIA
- Beneficiary
- COMUNE DI ALBEROBELLO
Programming area
- Programme
- PSC REGIONE PUGLIA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 922,741.61
- Payments on cohesion funds
- € 185,304.03
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici