CUP: J71B11000630001
CIRCONVALLAZIONE NARDO' III LOTTO
SUMMARY OF THE PROJECT
CIRCONVALLAZIONE NARDO' III LOTTO
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 1,718 m
- Achieved
- 1,718 m
Funding monitored
€ 5,000,000.00
of which cohesion funds
€ 5,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 5000000.00 |
Payments monitored
€ 2,198,704.98
of which cohesion funds
€ 2,198,704.98
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 2095.56 | 2095.56 | 0 |
2015 | 151303.82 | 153399.38 | 3 |
2016 | 15164.18 | 168563.56 | 3 |
2017 | 1370874.72 | 1539438.28 | 30 |
2018 | 659266.70 | 2198704.98 | 43 |
State of progress
Open
Expected start: 31/12/2015
Effective start: not available
Expected end: 31/12/2015
Effective end: not available
Entities
- Planning body
- REGIONE PUGLIA
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI LECCE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE PUGLIA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale