CUP: H71C18000050002
REALIZZAZIONE PIATTAFORMA LOGISTICA FERROVIARIA INTEGRATA - STRADE/VIABILITA'
SUMMARY OF THE PROJECT
REALIZZAZIONE PIATTAFORMA LOGISTICA FERROVIARIA INTEGRATA - STRADE/VIABILITA'
Implementation indicator
Superficie oggetto di intervento
- Target
- 95,000 mq
- Achieved
- 0 mq
Funding monitored
€ 17,825,136.11
of which cohesion funds
€ 17,825,136.11
Given name | Amount |
---|---|
Development and Cohesion Fund | 17825136.11 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 20/02/2024
Effective start: not available
Expected end: 17/08/2025
Effective end: not available
Entities
- Planning body
- REGIONE PUGLIA
- Beneficiary
- CONSORZIO PER L'AREA DI SVILUPPO INDUSTRIALE DI FOGGIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE PUGLIA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Logistica