CUP: J83H19001950004
RIQUALIFICAZIONE E MESSA IN SICUREZZA, REALIZZAZIONE DI NUOVA PISTA CICLABILE SU VIA TORRETTA - BRINDISI
SUMMARY OF THE PROJECT
RIQUALIFICAZIONE E MESSA IN SICUREZZA, REALIZZAZIONE DI NUOVA PISTA CICLABILE SU VIA TORRETTA - BRINDISI
Implementation indicator
Superficie oggetto di intervento
- Target
- 450 mq
- Achieved
- 450 mq
Download project
Funding monitored
€ 571,660.48
of which cohesion funds
€ 571,660.48
Given name | Amount |
---|---|
European Union | 457328.38 |
Revolving Fund | 80032.47 |
Region | 34299.63 |
Payments monitored
€ 548,786.60
of which cohesion funds
€ 548,786.60
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 12728.05 | 12728.05 | 2 |
2021 | 16145.46 | 28873.51 | 5 |
2022 | 95287.34 | 124160.85 | 21 |
2023 | 424625.75 | 548786.60 | 95 |
State of progress
Completed
Expected start: 01/09/2021
Effective start: 18/03/2022
Expected end: 28/02/2023
Effective end: 30/11/2023
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
-
PROFIN SERVICE SRL
LAPENNA MICHELE ROBERTO
GESUALDI S.R.L
DODI MOSS S.R.L
COMUNE DI BRINDISI - Beneficiary
- COMUNE DI BRINDISI
Programming area
- Programme
- ROP ERDF ESF APULIA
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 571,660.48
- Payments on cohesion funds
- € 548,786.60
- Axis
- Sviluppo Urbano Sostenibile
- Specific objective
- Aumentare la mobilità sostenibile nelle aree urbane