CUP: H76E18000120001
INTERVENTO DI EDILIZIA SCOLASTICA DEL COMUNE DI POGGIARDO. SCUOLA MEDIA DI VIA MONTE GRAPPA
SUMMARY OF THE PROJECT
INTERVENTO DI EDILIZIA SCOLASTICA DEL COMUNE DI POGGIARDO. SCUOLA MEDIA DI VIA MONTE GRAPPA
Download project
Funding monitored
€ 783,513.75
of which cohesion funds
€ 783,513.75
Given name | Amount |
---|---|
European Union | 626811.00 |
Revolving Fund | 109691.93 |
Region | 47010.82 |
Payments monitored
€ 337,042.75
of which cohesion funds
€ 337,042.75
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 337042.75 | 337042.75 | 43 |
State of progress
Open
Expected start: 12/06/2023
Effective start: 12/06/2023
Expected end: 31/12/2023
Effective end: not available
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
-
PISANELLO CARMINE
ELIA RESTAURI S.R.L
CARBONE VINCENZO
AGENZIA DELLE ENTRATE - Beneficiary
- COMUNE DI POGGIARDO
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF ESF APULIA
- Axis
- INVESTIRE NELL'ISTRUZIONE, NELLA FORMAZIONE E NELLA FORMAZIO
- Specific objective
- Aumentare la propensione dei giovani a permanere nei contesti formativi e migliorare la sicurezza e la fruibilità degli ambienti scolastici