CUP: G73G15000300001
POTENZIAMENTO E VELOCIZZAZIONE LINEA FERROVIARIA BARI-MATERA LOTTO5 MELLITTO-TORITTO E PESCARIELLO-ALTAMURA
SUMMARY OF THE PROJECT
POTENZIAMENTO E VELOCIZZAZIONE LINEA FERROVIARIA BARI-MATERA LOTTO5 MELLITTO-TORITTO E PESCARIELLO-ALTAMURA
Funding monitored
€ 9,666,856.68
of which cohesion funds
€ 9,666,856.68
Given name | Amount |
---|---|
European Union | 7733485.34 |
Revolving Fund | 1353359.94 |
Region | 580011.40 |
Payments monitored
€ 9,666,856.68
of which cohesion funds
€ 9,666,856.68
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 6570169.77 | 6570169.77 | 67 |
2017 | 2536600.00 | 9106769.77 | 94 |
2018 | 510900.00 | 9617669.77 | 99 |
2019 | 49186.91 | 9666856.68 | 100 |
State of progress
Completed
Expected start: 01/09/2016
Effective start: 01/09/2016
Expected end: 12/10/2017
Effective end: 12/10/2017
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- FRANCESCO VENTURA COSTRUZIONI FERROVIARIE S.R.L
- Beneficiary
- FERROVIE APPULO LUCANE SRL
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF ESF APULIA
- Axis
- PROMUOVERE SISTEMI DI TRASPORTO SOSTENIBILI ED ELIMINARE LE
- Specific objective
- Potenziare il sistema ferroviario regionale l¿integrazione modale e il miglioramento dei collegamenti multimodali con i principali nodi urbani, produttivi e logistici e la rete centrale, globale e lo
Other projects in territory
Same theme
RADDOPPIO BARI S. ANDREA - BITETTO | € 421,465,928 |
BARI SUD (BARI CENTRALE - BARI TORRE A MARE) | € 391,000,000 |
RADDOPPIO BARI-TARANTO E CTC INTERA LINEA | € 151,604,004 |
BRETELLA FERROVIARIA DEL SUD - EST BARESE | € 112,244,278 |