CUP: F26B20000880002
REALIZZAZIONE SISTEMA DI GESTIONE ACQUE PLUVIALI NEL COMUNE DI SAN GIOVANNI ROTONDO
SUMMARY OF THE PROJECT
REALIZZAZIONE SISTEMA DI GESTIONE ACQUE PLUVIALI NEL COMUNE DI SAN GIOVANNI ROTONDO
Implementation indicator
Superficie coperta
- Target
- 940 kmq
- Achieved
- 0 kmq
Funding monitored
€ 1,027,475.20
of which cohesion funds
€ 1,027,475.20
Given name | Amount |
---|---|
European Union | 821980.16 |
Revolving Fund | 143846.53 |
Region | 61648.51 |
Payments monitored
€ 490,413.74
of which cohesion funds
€ 490,413.74
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 160713.74 | 160713.74 | 15 |
2023 | 329700.00 | 490413.74 | 47 |
State of progress
Open
Expected start: 30/12/2019
Effective start: 31/01/2022
Expected end: 30/09/2023
Effective end: 31/01/2022
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- GEOM. IANNO MICHELE COSTRUZIONI
- Beneficiary
- COMUNE DI SAN GIOVANNI ROTONDO
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF ESF APULIA
- Axis
- TUTELA DELL'AMBIENTE E PROMOZIONE DELLE RISORSE NATURALI E C
- Specific objective
- Mantenere e migliorare la qualità dei corpi idrici