CUP: E52I11000120005
POTENZIAMENTO DELL'IMPIANTO DI DEPURAZIONE A SERVIZIO DELL'AGGLOMERATO DI FASANO "FORCATELLA" (BR)
SUMMARY OF THE PROJECT
POTENZIAMENTO DELL'IMPIANTO DI DEPURAZIONE A SERVIZIO DELL'AGGLOMERATO DI FASANO "FORCATELLA" (BR)
Implementation indicator
Popolazione addizionale beneficiaria del trattamento delle acque reflue potenziato
- Target
- 61,130 num
- Achieved
- 0 num
Funding monitored
€ 3,262,500.00
of which cohesion funds
€ 3,262,500.00
Given name | Amount |
---|---|
European Union | 2610000.00 |
Revolving Fund | 456750.00 |
Region | 195750.00 |
- Other resources - Private:
- € 1,087,500
Payments monitored
€ 30,913.38
of which cohesion funds
€ 30,913.38
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 30913.38 | 30913.38 | 0 |
State of progress
Open
Expected start: 04/10/2017
Effective start: not available
Expected end: 03/11/2018
Effective end: not available
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- C.C.C. CANTIERI COSTRUZIONI CEMENTO S.P.A
- Beneficiary
- ACQUEDOTTO PUGLIESE SPA
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF ESF APULIA
- Axis
- TUTELA DELL'AMBIENTE E PROMOZIONE DELLE RISORSE NATURALI E C
- Specific objective
- Migliorare il Servizio Idrico Integrato per usi civili e ridurre le perdite di rete di acquedotto