CUP: E61B14000480005
INTERVENTO DI COMPLETAMENTO DEL SERVIZIO IDRICO E FOGNANTE NELL'ABITATO DEL COMUNE DI MURO LECCESE (LE)
SUMMARY OF THE PROJECT
INTERVENTO DI COMPLETAMENTO DEL SERVIZIO IDRICO E FOGNANTE NELL'ABITATO DEL COMUNE DI MURO LECCESE (LE)
Implementation indicator
Popolazione addizionale beneficiaria del trattamento delle acque reflue potenziato
- Target
- 94 num
- Achieved
- 178 num
Download project
Funding monitored
€ 907,943.35
of which cohesion funds
€ 907,943.35
Given name | Amount |
---|---|
European Union | 726354.68 |
Revolving Fund | 127112.07 |
Region | 54476.60 |
- Other resources - Private:
- € 302,648
Payments monitored
€ 742,380.28
of which cohesion funds
€ 742,380.28
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 964.70 | 964.70 | 0 |
2017 | 8040.56 | 9005.26 | 0 |
2018 | 2813.66 | 11818.92 | 1 |
2019 | 16149.81 | 27968.73 | 3 |
2020 | 303870.12 | 331838.85 | 36 |
2021 | 409301.68 | 741140.53 | 81 |
2022 | 0 | 741140.53 | 81 |
2023 | 1239.75 | 742380.28 | 81 |
State of progress
Open
Expected start: 21/12/2020
Effective start: 21/12/2020
Expected end: 03/06/2021
Effective end: 03/06/2021
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
-
¿IMPRESA COSTRUZIONI GEOM. GIULIO SCIVOLETTO
SOCIETA COOPERATIVA ARCHEOLOGIA BREVEMENTE DETTA COOPERATIVA ARCHEOLOGIA
SCOMMEGNA ANGELA
SALCUNI LUCA
MUSA S.R.L
LOVINO FRANCESCO
ELIOGRAFIA SICILIANI S.A.S
ASTRA ENGINEERING S.R.L - Beneficiary
- ACQUEDOTTO PUGLIESE SPA
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF ESF APULIA
- Axis
- TUTELA DELL'AMBIENTE E PROMOZIONE DELLE RISORSE NATURALI E C
- Specific objective
- Migliorare il Servizio Idrico Integrato per usi civili e ridurre le perdite di rete di acquedotto