CUP: J75E17000050002
Altamura - Intervento di ristrutturazione e adeguamento sismico della scuola secondaria "Ottavio Serena
SUMMARY OF THE PROJECT
Altamura - Intervento di ristrutturazione e adeguamento sismico della scuola secondaria "Ottavio Serena
Implementation indicator
Superficie oggetto di intervento
- Target
- 4,292 mq
- Achieved
- 0 mq
Download project
Funding monitored
€ 2,682,869.89
of which cohesion funds
€ 2,682,869.89
Given name | Amount |
---|---|
European Union | 2146295.92 |
Revolving Fund | 375601.78 |
Region | 160972.19 |
Payments monitored
€ 884,255.10
of which cohesion funds
€ 884,255.10
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 641755.10 | 641755.10 | 23 |
2024 | 242500.00 | 884255.10 | 32 |
State of progress
Open
Expected start: 15/11/2022
Effective start: 24/01/2023
Expected end: 15/12/2022
Effective end: not available
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
-
STUDIO AMATI SRL
STC MANAGING SRLS
REGIONE PUGLIA
PERRUCCI VITO
PEPE PIETRO
LORUSSO MICHELE 2
ISTITUTO POLIGRAFICO E ZECCA DELLO STATO
I.RES
GALETTA NICOLA
GALETTA FRANCESCO
Visualizzati i primi 10 soggetti di 16 - Beneficiary
- COMUNE DI ALTAMURA
Programming area
- Programme
- ROP ERDF ESF APULIA
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 2,682,869.89
- Payments on cohesion funds
- € 884,255.10
- Axis
- ADATTAMENTO AL CAMBIAMENTO CLIMATICO, PREVENZIONE E GESTIONE
- Specific objective
- Ridurre il rischio incendi e il rischio sismico sul territorio regionale