CUP: E97C18000340004
n. 64 alloggi in BARI, via Livatino nn. 20-21-22-23-24-25-26-27
SUMMARY OF THE PROJECT
n. 64 alloggi in BARI, via Livatino nn. 20-21-22-23-24-25-26-27
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 119 KWh/a
- Achieved
- 0 KWh/a
Download project
Funding monitored
€ 828,478.26
of which cohesion funds
€ 828,478.26
Given name | Amount |
---|---|
European Union | 662782.61 |
Revolving Fund | 115986.96 |
Region | 49708.69 |
Payments monitored
€ 331,087.10
of which cohesion funds
€ 331,087.10
39%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 29458.67 | 29458.67 | 3 |
2022 | 124002.52 | 153461.19 | 18 |
2023 | 80497.16 | 233958.35 | 28 |
2024 | 97128.75 | 331087.10 | 39 |
State of progress
Open
Expected start: 31/12/2024
Effective start: not available
Expected end: 31/12/2024
Effective end: not available
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
-
POMARICO PAOLA
LEONARDO MAGGIO
FINEPRO SRL
FERRETTI GIANNI
EDIL DOMUS
CENTRONE MASSIMO
ADELE MARCELLO - Beneficiary
- AGENZIA REGIONALE PER LA CASA E L' ABITARE - A.R.C.A. PUGLIA CENTRALE
Programming area
- Programme
- ROP ERDF ESF APULIA
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 828,478.26
- Payments on cohesion funds
- € 331,087.10
- Axis
- Energia sostenibile e qualità della vita
- Specific objective
- Ridurre i consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non, e integrare le fonti rinnovabili