CUP: F48C08000030004
Adeguamento sismico della Scuola Materna "Don Milani"
Download project
Funding monitored
€ 975,998.14
of which cohesion funds
€ 593,076.75
Given name | Amount |
---|---|
European Union | 101425.83 |
Revolving Fund (National co-financing) | 156686.77 |
Region | 18885.54 |
Municipality | 699000.00 |
Payments monitored
€ 792,155.71
of which cohesion funds
€ 550,419.61
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 14697.65 | 14697.65 | 1 |
2009 | 16406.27 | 31103.92 | 3 |
2010 | 0 | 31103.92 | 3 |
2011 | 297931.73 | 329035.65 | 33 |
2012 | 429618.87 | 758654.52 | 77 |
2013 | 33501.19 | 792155.71 | 81 |
State of progress
Open
Expected start: 23/05/2011
Effective start: 23/05/2011
Expected end: 20/07/2012
Effective end: 08/08/2012
Type
- Infrastructure
- RISTRUTTURAZIONE
Theme
- Environment
- Prevenzione dei rischi (inclusa elaborazione e attuazione di piani e provvedimenti))
Territory
Entities
- Planning body
- REGIONE TOSCANA
- Implementing body
- COMUNE DI BARBERINO DI MUGELLO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- Programme
- ROP RCE ERDF TUSCANY
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 593,076.75
- Payments on cohesion funds
- € 550,419.61
- Axis
- Sostenibilità ambientale
- Operational objective
- Prevenire e sostenere la gestione dei rischi naturali e tecnologici.
Other projects in territory
Same theme
Same type of investment
Adeguamento sismico scuola elementare Galliano | € 383,423 |