CUP: D38I16000000008
LOGISTICA INTELLIGENTE DEL FARMACO
SUMMARY OF THE PROJECT
LOGISTICA INTELLIGENTE DEL FARMACO
Implementation indicator
Giornate uomo prestate
- Target
- 4,840.62 num
- Achieved
- 4,840.62 num
Funding monitored
€ 795,805.61
of which cohesion funds
€ 422,401.65
Given name | Amount |
---|---|
Development and Cohesion Fund | 422401.65 |
Region | 373403.96 |
- Other resources - Private:
- € 415,449
Payments monitored
€ 795,805.61
of which cohesion funds
€ 422,401.65
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 174240.85 | 174240.85 | 21 |
2017 | 134252.63 | 308493.48 | 38 |
2018 | 247751.35 | 556244.83 | 69 |
2019 | 0 | 556244.83 | 69 |
2020 | 239560.78 | 795805.61 | 100 |
State of progress
Completed
Expected start: 08/09/2016
Effective start: 08/09/2016
Expected end: 07/09/2018
Effective end: 08/03/2019
Entities
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE TOSCANA
- Policy Area
- Ricerca e Innovazione
- Sector of intervention
- Ricerca e Sviluppo