CUP: C83B06000130004
LAVORI DI REALIZZAZIONE SCUOLA DELL'INFANZIA
SUMMARY OF THE PROJECT
LAVORI DI REALIZZAZIONE SCUOLA DELL'INFANZIA
Implementation indicator
Superficie oggetto di intervento
- Target
- 862.29 mq
- Achieved
- 862.29 mq
Download project
Funding monitored
€ 946,000.00
of which cohesion funds
€ 441,254.99
Given name | Amount |
---|---|
Development and Cohesion Fund | 441254.99 |
Municipality | 504745.01 |
Payments monitored
€ 935,599.52
of which cohesion funds
€ 441,254.98
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 22214.36 | 22214.36 | 2 |
2008 | 4488.00 | 26702.36 | 2 |
2009 | 628.48 | 27330.84 | 2 |
2010 | 345254.56 | 372585.40 | 39 |
2011 | 296782.25 | 669367.65 | 70 |
2012 | 192393.77 | 861761.42 | 91 |
2013 | 73838.10 | 935599.52 | 98 |
State of progress
Completed
Expected start: 09/12/2009
Effective start: 09/12/2009
Expected end: 09/12/2009
Effective end: 09/12/2009
Entities
- Planning body
- REGIONE TOSCANA
- Beneficiary
- COMUNE DI QUARRATA
Programming area
- Programme
- PSC REGIONE TOSCANA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 441,254.99
- Payments on cohesion funds
- € 441,254.98
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative
Other projects in territory
Same theme
NUOVA MAPPA THE CATCHER IN THE RYE | € 62,023 |
SCHOOL TIME | € 61,302 |
APPROVARICERCA | € 50,000 |
SCUOLA COMPETENTE | € 48,681 |
IL VERO GIARDINIERE NON SI ARRENDE | € 48,681 |
Same type of investment
QUA_04_5.1B / PROGETTO RIFACIMENTO PIAZZA RISORGIMENTO A QUARRATA | € 1,859,751 |
RISTRUTTURAZIONE DELLA PALESTRA POLIFUNZIONALE DENOMINATA "PALAMELO" | € 267,551 |