CUP: D39D14001640008
1292/2013 - RIQUALIFICAZIONE BAGNI PARRINI
SUMMARY OF THE PROJECT
1292/2013 - RIQUALIFICAZIONE BAGNI PARRINI
Download project
Funding monitored
€ 176,493.29
of which cohesion funds
€ 176,493.29
Given name | Amount |
---|---|
Development and Cohesion Fund | 176493.29 |
- Other resources - Private:
- € 270,140
Payments monitored
€ 176,493.29
of which cohesion funds
€ 176,493.29
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 176493.29 | 176493.29 | 100 |
State of progress
Completed
Expected start: 25/02/2013
Effective start: 25/02/2013
Expected end: 09/03/2013
Effective end: 17/06/2016
Entities
- Planning body
- REGIONE TOSCANA
- Beneficiary
- RICCI SERENA
Programming area
- Programme
- PSC REGIONE TOSCANA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 176,493.29
- Payments on cohesion funds
- € 176,493.29
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Turismo e ospitalita'
Other projects in territory
Same theme
FOL_01_5.1B / AREA MERCATALE | € 6,207,270 |
(5985.29032022.215000008) INNOVAMAREMMA | € 287,571 |
(7012.22052017.109000073) VMS | € 191,867 |
(14508.17092020.172000464) C.A.I.M. 4.0 | € 99,750 |
(14508.17092020.172000658) ELMAR | € 99,019 |
Same type of investment
IL DIGITALE A FOLLONICA | € 35,750 |