CUP: E16J12000310002
V02 / Messa in sicurezza e recupero ponte Groppodalosio.
SUMMARY OF THE PROJECT
V02 / Messa in sicurezza e recupero ponte Groppodalosio.
Download project
Funding monitored
€ 67,582.66
of which cohesion funds
€ 67,582.66
Given name | Amount |
---|---|
Development and Cohesion Fund | 67582.66 |
- Economies:
- € 721.34
Payments monitored
€ 67,582.66
of which cohesion funds
€ 67,582.66
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 65265.64 | 65265.64 | 96 |
2015 | 2556.18 | 67821.82 | 100 |
2016 | 0 | 67821.82 | 100 |
2017 | 0 | 67821.82 | 100 |
2018 | 0 | 67821.82 | 100 |
2019 | 0 | 67821.82 | 100 |
2020 | 0 | 67821.82 | 100 |
2021 | 0 | 67821.82 | 100 |
2022 | -239.16 | 67582.66 | 100 |
State of progress
Completed
Expected start: 01/09/2014
Effective start: 01/09/2014
Expected end: 29/11/2014
Effective end: 10/12/2014
Entities
- Planning body
- REGIONE TOSCANA
- Beneficiary
- COMUNE DI PONTREMOLI
Programming area
- Programme
- PSC REGIONE TOSCANA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 67,582.66
- Payments on cohesion funds
- € 67,582.66
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Turismo e ospitalita'