CUP: I33B06000070006
ADEGUAMENTO SISMICO DELL'ITC (Istituto Tecnico Commerciale) NEL COMUNE DI POPPI (AR)
Download project
Funding monitored
€ 1,162,766.05
of which cohesion funds
€ 1,080,638.29
Given name | Amount |
---|---|
European Union | 84378.22 |
Revolving Fund (National co-financing) | 130350.93 |
Region | 15711.27 |
Province | 932325.63 |
- Economies:
- € 998.43
Payments monitored
€ 1,162,766.05
of which cohesion funds
€ 1,068,213.98
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 600.00 | 600.00 | 0 |
2013 | 265437.84 | 266037.84 | 22 |
2014 | 747976.92 | 1014014.76 | 87 |
2015 | 148751.29 | 1162766.05 | 100 |
State of progress
Completed
Expected start: 24/06/2013
Effective start: 24/06/2013
Expected end: 25/06/2015
Effective end: 25/06/2015
Type
- Infrastructure
- RISTRUTTURAZIONE
Theme
- Environment
- Prevenzione dei rischi (inclusa elaborazione e attuazione di piani e provvedimenti))
Territory
Entities
- Planning body
- REGIONE TOSCANA
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI AREZZO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- Programme
- ROP RCE ERDF TUSCANY
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 1,080,638.29
- Payments on cohesion funds
- € 1,068,213.98
- Axis
- Sostenibilità ambientale
- Operational objective
- Prevenire e sostenere la gestione dei rischi naturali e tecnologici.
Other projects in territory