CUP: H17H10000870004
FI_01_51A / LE MURATE
SUMMARY OF THE PROJECT
FI_01_51A / LE MURATE
Implementation indicator
Estensione in lunghezza
- Target
- 1 km
- Achieved
- 0 km
Funding monitored
€ 576,408.44
of which cohesion funds
€ 247,399.53
Given name | Amount |
---|---|
Development and Cohesion Fund | 247399.53 |
Municipality | 329008.91 |
- Economies:
- € 127,391.56
Payments monitored
€ 547,636.87
of which cohesion funds
€ 247,399.53
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2011 | 341892.29 | 341892.29 | 59 |
2012 | 205744.58 | 547636.87 | 95 |
State of progress
Completed
Expected start: 21/03/2011
Effective start: 21/03/2011
Expected end: 30/08/2012
Effective end: 30/05/2012
Entities
- Planning body
- REGIONE TOSCANA
- Beneficiary
- COMUNE DI FIRENZE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE TOSCANA
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Industria e servizi
Other projects in territory
Same theme
REALIZZAZIONE TRAMVIA NELL'AREA METROPOLITANA FIORENTINA | € 406,558,409 |
SISTEMA TRAMVIARIO LINEA 4 - LEOPOLDA - PIAGGE | € 169,550,000 |
ADEGUAMENTO IDRAULICO DEL TORRENTE MUGNONE. | € 45,283,349 |
LINEA 2 TRATTA 2 VARIANTE ALTERNATIVA AL CENTRO STORICO | € 41,487,176 |
ASSE FIRENZE MEZZANA LOTTI 5A - LAVORI PRINCIPALI | € 14,571,586 |