CUP: E82J10000220002
LAVORI DI SOMMA URGENZA PER RIPRISTINO MOVIMENTO FRANOSOA MONTE E A VALLE DELLA STRADA PROVINCIALE 72 IN LOCALITA' SANTA CATERINA
SUMMARY OF THE PROJECT
LAVORI DI SOMMA URGENZA PER RIPRISTINO MOVIMENTO FRANOSOA MONTE E A VALLE DELLA STRADA PROVINCIALE 72 IN LOCALITA' SANTA CATERINA
Implementation indicator
Superficie oggetto di intervento
- Target
- 10,000 mq
- Achieved
- 10,000 mq
Funding monitored
€ 1,666,329.21
of which cohesion funds
€ 1,171,073.47
Given name | Amount |
---|---|
Development and Cohesion Fund | 1171073.47 |
Region | 495255.74 |
Payments monitored
€ 1,666,329.21
of which cohesion funds
€ 1,171,073.45
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2010 | 903154.96 | 903154.96 | 54 |
2011 | 690559.76 | 1593714.72 | 95 |
2012 | 11637.75 | 1605352.47 | 96 |
2013 | 55978.36 | 1661330.83 | 99 |
2014 | 5769.96 | 1667100.79 | 100 |
2015 | 0 | 1667100.79 | 100 |
2016 | 0 | 1667100.79 | 100 |
2017 | 0 | 1667100.79 | 100 |
2018 | 0 | 1667100.79 | 100 |
2019 | 0 | 1667100.79 | 100 |
2020 | 0 | 1667100.79 | 100 |
2021 | 0 | 1667100.79 | 100 |
2022 | -771.58 | 1666329.21 | 100 |
State of progress
Completed
Expected start: 28/01/2010
Effective start: 28/01/2010
Expected end: 29/12/2011
Effective end: 29/12/2011
Entities
- Planning body
- REGIONE TOSCANA
- Beneficiary
- COMUNE DI CASTIGLIONE DI GARFAGNANA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE TOSCANA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico
Other projects in territory
Same theme
28 - INTERVENTI DI CONTENIMENTO DEL MATERIALE COMBUSTIBILE A TERRA AI FINI DELLA PREVENZIONE DEGLI INCENDI BOSCHIVI | € 28,315 |