CUP: H15D10000020003
Completamento lavori di difesa spondale in loc. S.Giustina
SUMMARY OF THE PROJECT
Completamento lavori di difesa spondale in loc. S.Giustina
Implementation indicator
Superficie oggetto di intervento
- Target
- 300 mq
- Achieved
- 300 mq
Download project
Funding monitored
€ 247,205.39
of which cohesion funds
€ 173,732.58
Given name | Amount |
---|---|
Development and Cohesion Fund | 173732.58 |
Region | 73472.81 |
Payments monitored
€ 247,205.39
of which cohesion funds
€ 173,732.58
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2010 | 150.00 | 150.00 | 0 |
2011 | 245501.65 | 245651.65 | 99 |
2012 | 0 | 245651.65 | 99 |
2013 | 0 | 245651.65 | 99 |
2014 | 0 | 245651.65 | 99 |
2015 | 0 | 245651.65 | 99 |
2016 | 1553.74 | 247205.39 | 100 |
State of progress
Completed
Expected start: 15/10/2010
Effective start: 15/10/2010
Expected end: 13/01/2011
Effective end: 06/06/2011
Entities
- Planning body
- REGIONE TOSCANA
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI MASSA CARRARA
Programming area
- Programme
- PSC REGIONE TOSCANA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 173,732.58
- Payments on cohesion funds
- € 173,732.58
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico
Other projects in territory
Same theme
messa in sicurezza area in frana loc Succisa | € 2,923,418 |
Consolidamento frana su SC in loc. Pra del Prete | € 692,382 |
Consolidamento frana su SC in loc. Cavezzana Gordana | € 460,511 |