CUP: F67D07000000004
Realizzazione opere di urbanizzazione P.I.P di Pomarance
SUMMARY OF THE PROJECT
Realizzazione opere di urbanizzazione P.I.P di Pomarance
Implementation indicator
Superficie oggetto di intervento
- Target
- 69,052 mq
- Achieved
- 69,052 mq
Download project
Funding monitored
€ 2,396,846.70
of which cohesion funds
€ 778,222.82
Given name | Amount |
---|---|
Development and Cohesion Fund | 778222.82 |
Municipality | 1618623.88 |
- Economies:
- € 230,899.93
Payments monitored
€ 2,122,119.35
of which cohesion funds
€ 778,222.81
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 958716.48 | 958716.48 | 39 |
2010 | 290061.60 | 1248778.08 | 52 |
2011 | 488778.37 | 1737556.45 | 72 |
2012 | 154791.88 | 1892348.33 | 78 |
2013 | 18248.76 | 1910597.09 | 79 |
2014 | 211522.26 | 2122119.35 | 88 |
State of progress
Open
Expected start: 26/01/2009
Effective start: 26/01/2009
Expected end: 31/08/2014
Effective end: 01/08/2014
Entities
- Planning body
- REGIONE TOSCANA
- Beneficiary
- COMUNE DI POMARANCE
Programming area
- Programme
- PSC REGIONE TOSCANA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 778,222.82
- Payments on cohesion funds
- € 778,222.81
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Industria e servizi