CUP: E71B03000070001
TANGENZIALE SUD DI BERGAMO - 1° LOTTO - 2° STRALCIO
SUMMARY OF THE PROJECT
TANGENZIALE SUD DI BERGAMO - 1° LOTTO - 2° STRALCIO
Implementation indicator
Estensione in lunghezza
- Target
- 6.28 km
- Achieved
- 6.20 km
Download project
Funding monitored
€ 45,928,656.27
of which cohesion funds
€ 25,911,586.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 25911586.00 |
Region | 20017070.27 |
Payments monitored
€ 45,928,656.27
of which cohesion funds
€ 25,911,586.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 45928656.27 | 45928656.27 | 100 |
State of progress
Completed
Expected start: 05/11/2007
Effective start: 05/11/2007
Expected end: 24/03/2010
Effective end: 24/03/2010
Entities
- Planning body
- REGIONE LOMBARDIA
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI BERGAMO
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI BERGAMO
- Executor
- AMMINISTRAZIONE PROVINCIALE DI BERGAMO
Programming area
- Programme
- PSC REGIONE LOMBARDIA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 25,911,586.00
- Payments on cohesion funds
- € 25,911,586.00
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale