CUP: C57B17000160002
Completamento opere per la messa in sicurezza dei versanti a monte degli abitati di Piamborno e Cogno
SUMMARY OF THE PROJECT
Messa in sicurezza dei versanti rocciosi mediante pulizia e disgaggio, posa in opera di barriere paramassi.
Implementation indicator
Superficie oggetto di intervento
- Target
- 3,200 mq
- Achieved
- 3,200 mq
Download project
Funding monitored
€ 572,368.75
of which cohesion funds
€ 572,368.75
Given name | Amount |
---|---|
Development and Cohesion Fund | 572368.75 |
- Economies:
- € 1,832.00
Payments monitored
€ 572,368.75
of which cohesion funds
€ 572,368.75
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 572368.75 | 572368.75 | 100 |
State of progress
Completed
Expected start: 30/09/2018
Effective start: 08/04/2019
Expected end: 31/05/2019
Effective end: 11/10/2019
Entities
- Planning body
- REGIONE LOMBARDIA
- Implementing body
- COMUNE DI PIANCOGNO
- Beneficiary
- COMUNE DI PIANCOGNO
- Executor
- DAPAM Srl Impresa di costruzioni
Programming area
- Programme
- PSC REGIONE LOMBARDIA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 572,368.75
- Payments on cohesion funds
- € 572,368.75
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico