CUP: B84H16000130006
PROGETTO PRELIMINARE INCUDINE
SUMMARY OF THE PROJECT
PROGETTO PRELIMINARE INCUDINE
Implementation indicators
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 100,400.97 KWh/a
- Achieved
- 100,400.97 KWh/a
Diminuzione annuale stimata dei gas a effetto serra
- Target
- 36.36 teq
- Achieved
- 21.12 teq
Superficie oggetto di intervento
- Target
- 340.66 mq
- Achieved
- 340.66 mq
- Slide 1
- Slide 2
- Slide 3
Download project
Funding monitored
€ 185,348.07
of which cohesion funds
€ 185,348.07
Given name | Amount |
---|---|
European Union | 92674.04 |
Status: other measures | 64871.82 |
Region | 27802.21 |
Payments monitored
€ 185,348.07
of which cohesion funds
€ 185,348.07
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 185348.07 | 185348.07 | 100 |
State of progress
Completed
Expected start: 23/07/2018
Effective start: 23/07/2018
Expected end: 31/12/2019
Effective end: 31/12/2019
Entities
- Planning body
- REGIONE LOMBARDIA
- Implementing body
- COMUNE DI INCUDINE
- Beneficiary
- COMUNE DI INCUDINE
Programming area
- Programme
- ROP ERDF LOMBARDY
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 185,348.07
- Payments on cohesion funds
- € 185,348.07
- Axis
- SOSTENERE LA TRANSIZIONE VERSO UN'ECONOMIA A BASSE EMISSIONI
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili