CUP: E87B16001180007
FORMAZIONE CONTINUA FASE IV PROGETTI AZIENDALI- BN 322
SUMMARY OF THE PROJECT
FORMAZIONE CONTINUA FASE IV PROGETTI AZIENDALI- BN 322 - AGGIORNAMENTO DELLE COMPETENZE E FORMAZIONE FORMATORI IN AFOL
Implementation indicators
Lavoratori, compresi i lavoratori autonomi (femmine)
- Target
- 81 persone
- Achieved
- 78 persone
Lavoratori, compresi i lavoratori autonomi (maschi)
- Target
- 47 persone
- Achieved
- 46 persone
Numero di imprese finanziate
- Target
- 1 num
- Achieved
- 1 num
- Slide 1
- Slide 2
- Slide 3
Funding monitored
€ 99,467.55
of which cohesion funds
€ 99,467.55
Given name | Amount |
---|---|
European Union | 49733.78 |
Status: other measures | 34813.64 |
Region | 14920.13 |
Payments monitored
€ 99,467.55
of which cohesion funds
€ 99,467.55
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 99467.55 | 99467.55 | 100 |
State of progress
Completed
Expected start: 24/11/2016
Effective start: 23/11/2016
Expected end: 21/04/2017
Effective end: 21/04/2017
Entities
- Planning body
- REGIONE LOMBARDIA
- Implementing body
- REGIONE LOMBARDIA
- Beneficiary
- E-WORK S.P.A.
Programming area
- European Social Fund (ESF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ESF LOMBARDY
- Axis
- OCCUPAZIONE
- Specific objective
- Favorire la permanenza al lavoro e la ricollocazione dei lavoratori coinvolti in situazioni di crisi
Other projects in territory
Same theme
CASSA INTEGRAZIONE IN DEROGA (CIGD) | € 168,500,000 |
LOM71035450 | € 4,795,999 |
LOM7103661105 | € 2,214,796 |
LOM71036119 | € 1,764,600 |
LOM7103553647 | € 1,707,791 |