CUP: E37J18000070002
CONSOLIDAMENTO PONTE FERROVIARIO SUL FIUME TICINO
SUMMARY OF THE PROJECT
L'INTERVENTO CONSISTE NELLA REALIZZAZIONE DI INTERVENTI DI CONSOLIDAMENTO STRUTTURALE SIA ALLE PILE DI FONDAZIONE IN ALVEO, SIA ALLE SPALLE, SIA ALLA STRUTTURA METALLICA DEL PONTE E DELLE SOLETTE FERROVIARIA E STRADALE. OLTRE AL CONSOLIDAMENTO DERIVANTE DALLA NECESSARIA MANUTENZIONE STRAORDINARIA, AL TERMINE DEI LAVORI IL PONTE POTR ESSERE RIQUALIFICATO IN CATEGORIA D4 PER IL TRAFFICO FERROVIARIO E IN I CATEGORIA PER QUELLO STRADALE. L'INTERVENTO IN COORDINAMENTO CON ANAS, COMPROPRIETARIA DE
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 150 m
- Achieved
- -
Download project
Funding monitored
€ 5,000,000.00
of which cohesion funds
€ 5,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 5000000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 15/12/2019
Effective start: 05/03/2020
Expected end: 30/06/2023
Effective end: not available
Entities
- Planning body
- REGIONE LOMBARDIA
- Implementing body
- FERROVIENORD SOCIETA PER AZIONI
- Beneficiary
- REGIONE LOMBARDIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE LOMBARDIA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale