Updated on 30/04/2025
Funding monitored € 246,600.00 of which cohesion funds € 246,600.00
Given name Amount
Development and Cohesion Fund246600.00
Payments monitored € 246,600.00 of which cohesion funds € 246,600.00
Year Amount Cumulative amount Percentage on public financing
202061650.0061650.0025
2021141951.81203601.8182
202242998.19246600.00100

State of progress

Completed
Expected start: 16/04/2018
Effective start: 16/04/2018
Expected end: 23/12/2020
Effective end: 23/12/2020

Entities

Planning body
MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
Implementing body
AUTOLINEE GIACHINO
Beneficiary
REGIONE PIEMONTE

Programming area

Programme
PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Cohesion funds
€ 246,600.00
Payments on cohesion funds
€ 246,600.00
Policy Area
Trasporti e Mobilita'
Sector of intervention
Mobilita' urbana