CUP: I50H18000000001
Rinnovo materiale rotabile ferroviario (4 treni)
SUMMARY OF THE PROJECT
Acquisto di n. 4 elettrotreni a composizione bloccata
Implementation indicator
Unita' beni acquistati
- Target
- 4 num
- Achieved
- 0 num
Download project
Funding monitored
€ 17,664,000.00
of which cohesion funds
€ 17,664,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 17664000.00 |
Payments monitored
€ 3,513,839.02
of which cohesion funds
€ 3,513,839.02
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 3513839.02 | 3513839.02 | 19 |
State of progress
Open
Expected start: 01/01/2024
Effective start: not available
Expected end: 31/12/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- INFRASTRUTTURE VENETE S.R.L.
- Beneficiary
- REGIONE DEL VENETO
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 17,664,000.00
- Payments on cohesion funds
- € 3,513,839.02
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana
Other projects in territory
Same theme
Elettrificazione anello bellunese | € 230,000,000 |
Nuova SR. 10 "Padana Inferiore" | € 89,700,000 |
Elettrificazione linea Trento - Bassano | € 60,000,000 |
Elettrificazione della tratta ferroviaria Adria Mestre fra le stazioni di Adria e Mira Buse | € 40,750,000 |
Elettrificazione della tratta ferroviaria Adria - Mestre | € 40,750,000 |